SHL Numerical reasoning (word problems)
Verify Numerical Reasoning (standard) ยท Examples with explanations
Example 3 / 3
Quantitative reasoning
Two packing machines work on an order together. Machine A packs 240 boxes an hour, machine B 160 boxes an hour. Machine B is switched on an hour after machine A.
How many hours after machine A starts is an order of 2,640 boxes finished?